Hotel Salinera

Project statistics

Reduction of heating costs by

37

%

500

t

annual reduction of CO2 emissions

Situation before the contract and client requirements

The hotel was facing high energy expenses and an obsolete heating system that needed to be renovated; it needed to operate without interruptions.

The client was looking for a contracting partner with experience in energy solutions and financing.

Resalta solution

Resalta undertook a hydraulic reconstruction of the existing boiler room and installed a reversible heat pump sea water/water. This was connected to the existing pumping station and in addition new pipe connections were installed between the heat pump and the boiler room.

Resalta signed a contract for the energy supply of cooling and heating energy to the client.

Chcesz zobaczyć więcej?

Pobierz nasze badania

Regulamin

Zapisując się na naszego newslettera zgadzasz się na otrzymywanie wiadomości e-mail od Resalty Luneos Sp. z o. o. Celem naszego newslettera jest informowanie o działalności Resalta Luneos, nowych projektach, postępach, nadchodzących wydarzeniach oraz przekazywanie najświeższych doniesień dotyczących wydajności energetycznej i odnawialnych źródeł energii gościom odwiedzającym naszą stronę internetową, partnerom, klientom oraz opinii publicznej. Nasz newsletter będzie wydawany najczęściej raz w miesiącu, z wyjątkiem nieplanowanych, lecz ważnych wiadomości. Zastrzegamy sobie pełne prawo do modyfikacji lub zaprzestania publikowania newslettera, w każdym momencie bez powiadomienia. Traktujemy Twoją prywatność poważnie i nigdy nie przekażemy lub nie sprzedamy Twoich danych osobom trzecim. W każdej chwili możesz zrezygnować z subskrypcji newslettera.