Sava Hoteli, Radenci Hotel & Spa/CHP – Slovenia

Project statistics

Annual savings

220,000

EUR

Combined CHP efficiency is

86

%

Situation before the contract and client requirements

The Radenci Health Resort is one of the biggest health resorts in Slovenia. It has 10 pools with a total of 1,460 m2 of water surface. The resort used natural gas for heating, which required 8,500 MWh per year. The client wanted to lower heating costs. 

Resalta solution

Resalta did a careful analysis of the actual consumption of the resort in order to come up with the best solution. 

Resalta developed and installed a cogeneration plant (CHP) with a combined electrical power of 889 kW (43 % efficiency) and thermal power of 891 kW (43 % efficiency). 

The CHP plant has a lifespan of up to 70,000 operating hours - ensuring a minimum of 7,000 operating hours per year. 

Resalta operates and maintains the plant, sells heat and electric energy to the client and monitors the system through its central control system (web access) in real time.

Chcesz zobaczyć więcej?

Pobierz nasze badania

Regulamin

Zapisując się na naszego newslettera zgadzasz się na otrzymywanie wiadomości e-mail od Resalty Luneos Sp. z o. o. Celem naszego newslettera jest informowanie o działalności Resalta Luneos, nowych projektach, postępach, nadchodzących wydarzeniach oraz przekazywanie najświeższych doniesień dotyczących wydajności energetycznej i odnawialnych źródeł energii gościom odwiedzającym naszą stronę internetową, partnerom, klientom oraz opinii publicznej. Nasz newsletter będzie wydawany najczęściej raz w miesiącu, z wyjątkiem nieplanowanych, lecz ważnych wiadomości. Zastrzegamy sobie pełne prawo do modyfikacji lub zaprzestania publikowania newslettera, w każdym momencie bez powiadomienia. Traktujemy Twoją prywatność poważnie i nigdy nie przekażemy lub nie sprzedamy Twoich danych osobom trzecim. W każdej chwili możesz zrezygnować z subskrypcji newslettera.