Hotel Histrion – Slovenia

Project statistics

Supplied heating energy costs reduced by

69

%

Total heating costs reduced by

17

%

Cooling costs reduced by

37

%

Situation before the contract and client requirements

The hotel used two chillers with a combined power of 590 kW, with a 4-way piping system, for cooling, and for heating a boiler with extra light fuel oil.

The entire existing cooling and heating system was obsolete and the hotel was incurring high costs of energy.

During works, the hotel had to operate without interruptions. 

Resalta solution

Resalta replaced two old chillers with one reversible heat pump (air/water), 590 kW capacity with an integrated hydro module. 

In summer time the heat pump covers all the cooling demand, in winter time it is the primary heating source in combination with boilers. 

The existing boiler room was reconstructed to retain the existing system for peak demands. 

Resalta provides energy supply of cold and heat. The whole system is connected to Resalta‘s central control system.

Chcesz zobaczyć więcej?

Pobierz nasze badania

Regulamin

Zapisując się na naszego newslettera zgadzasz się na otrzymywanie wiadomości e-mail od Resalty Luneos Sp. z o. o. Celem naszego newslettera jest informowanie o działalności Resalta Luneos, nowych projektach, postępach, nadchodzących wydarzeniach oraz przekazywanie najświeższych doniesień dotyczących wydajności energetycznej i odnawialnych źródeł energii gościom odwiedzającym naszą stronę internetową, partnerom, klientom oraz opinii publicznej. Nasz newsletter będzie wydawany najczęściej raz w miesiącu, z wyjątkiem nieplanowanych, lecz ważnych wiadomości. Zastrzegamy sobie pełne prawo do modyfikacji lub zaprzestania publikowania newslettera, w każdym momencie bez powiadomienia. Traktujemy Twoją prywatność poważnie i nigdy nie przekażemy lub nie sprzedamy Twoich danych osobom trzecim. W każdej chwili możesz zrezygnować z subskrypcji newslettera.