Petrovac na Mlavi municipality – Serbia

Project statistics

savings once the contract expires

78.8

%

Electrical capacity decreased by 

165

kW

Situation before the contract and client requirements

Petrovac na Mlavi is a town in central Serbia. Its public lighting infrastructure was outdated and the municipality decided to publish a tender for a public private partnership to renovate the systems. Resalta won the tender with its technical partner Elios. 

Resalta solution

Resalta’s solution is to replace 1,521 old luminaires with 1,426 LED luminaires and 50 halogen luminaires. 

Resalta will also replace the obsolete systems for switching public lighting on and off at all 36 substations in the municipality, with an automated system that will enable greater energy efficiency. 

The PPP contract lasts 12 years, with Resalta providing an added 3 years of guarantee for the lighting equipment.

Chcesz zobaczyć więcej?

Pobierz nasze badania

Regulamin

Zapisując się na naszego newslettera zgadzasz się na otrzymywanie wiadomości e-mail od Resalty Luneos Sp. z o. o. Celem naszego newslettera jest informowanie o działalności Resalta Luneos, nowych projektach, postępach, nadchodzących wydarzeniach oraz przekazywanie najświeższych doniesień dotyczących wydajności energetycznej i odnawialnych źródeł energii gościom odwiedzającym naszą stronę internetową, partnerom, klientom oraz opinii publicznej. Nasz newsletter będzie wydawany najczęściej raz w miesiącu, z wyjątkiem nieplanowanych, lecz ważnych wiadomości. Zastrzegamy sobie pełne prawo do modyfikacji lub zaprzestania publikowania newslettera, w każdym momencie bez powiadomienia. Traktujemy Twoją prywatność poważnie i nigdy nie przekażemy lub nie sprzedamy Twoich danych osobom trzecim. W każdej chwili możesz zrezygnować z subskrypcji newslettera.