Slatina CHP – Croatia

Project statistics

15 new jobs created at the plant

Clean, cheap and efficient energy for the municipality

40

GWh

of electricity produced annually

Situation before the contract and client requirements

The Slatina project was launched to build a cogeneration heat and power plant that runs on biomass. It will be located in the northern part of Croatia in the Slatina municipality. 

The parcel on which the facility will be built is situated outside the city of Slatina on the building plot with the cadastral number 819/6, in possession of the company Energy 9. 

Resalta solution

Resalta will build a 5 MW cogeneration plant in Slatina. The plant includes a woodchip dryer. 

Slatina has signed a 14-year PPA with HROTE (Croatian electricity off taker). The project includes the electricity interconnection with a transmission system operator. 

A long-term supply contract for biomass has been signed with Hrvatske Šume for 14 years. 

Chcesz zobaczyć więcej?

Pobierz nasze badania

Regulamin

Zapisując się na naszego newslettera zgadzasz się na otrzymywanie wiadomości e-mail od Resalty Luneos Sp. z o. o. Celem naszego newslettera jest informowanie o działalności Resalta Luneos, nowych projektach, postępach, nadchodzących wydarzeniach oraz przekazywanie najświeższych doniesień dotyczących wydajności energetycznej i odnawialnych źródeł energii gościom odwiedzającym naszą stronę internetową, partnerom, klientom oraz opinii publicznej. Nasz newsletter będzie wydawany najczęściej raz w miesiącu, z wyjątkiem nieplanowanych, lecz ważnych wiadomości. Zastrzegamy sobie pełne prawo do modyfikacji lub zaprzestania publikowania newslettera, w każdym momencie bez powiadomienia. Traktujemy Twoją prywatność poważnie i nigdy nie przekażemy lub nie sprzedamy Twoich danych osobom trzecim. W każdej chwili możesz zrezygnować z subskrypcji newslettera.